Once the screed and floor finish are laid, the pipes are buried. Any leak found afterwards means opening the floor. That is why pressure testing before the screed is the most important step in handing over an underfloor heating system.
How do we test?
- We connect every loop to the manifold, fill it with water and purge the air.
- We raise the pressure above working pressure, following the pipe manufacturer instructions.
- We hold it and watch the gauge; if it drops there is a leak, which we find and fix.
- We record the reading and give it to the client in the handover file.


Why before the screed?
Fixing a leak at this stage takes minutes; after the screed it takes days and breaks the floor. We also keep the pressure on while the screed is poured, so any damage from other trades shows immediately.
Commissioning after handover
After the screed has fully cured (roughly three to four weeks depending on type) we start the system gradually, raising temperature over several days, not at once, to avoid cracking the screed.


What you receive
- Pressure test readings and date.
- A drawing of loop routes and manifold locations.
- Operation and maintenance instructions.
- A thermostat for each room.
Frequently asked questions
What pressure is used?
It depends on the pipe specification, and we follow the manufacturer instructions.
Why keep the drawing?
It protects the floor from nails and drilling later because it shows where the pipes run.
Does the warranty cover the network?
Yes: 20 years on the pipe network; boiler and pump equipment carries the manufacturer warranty.